    ETD explained

    Estimated Time of Departure

    The projected sailing date from the load port; factory lead times are usually planned backward from it.

    Full definition

    ETD anchors your payment schedule, insurance and ISF filing. In practice factories treat "ETD minus 7 days" as the warehouse cut-off, because export declaration, gate-in and loading all sit between. When a factory slips, confirm which vessel the new ETD refers to and whether it stays on the same service — a transshipment substitution adds both transit time and damage exposure.

    Worked examples

    • ETD Yantian 2026-04-02, cut-off 2026-03-29